Archive | December, 2013

Renovation Process: Week Six

16 Dec

Why is Week 5 missing? Well, my contractor was away on a cruise trip with his family. Good break for him! 🙂

When he was back on Week 6, he worked on the kitchen cabinets and we also discussed on how to install the bathroom accessories. Previously, I’ve mentioned that I’ve purposely chose different laminates and countertop for my main cabinets and side cabinets. Here’s the effect! What do you think? Does it look weird or good?

Renovation Process: Week Four

15 Dec

Week 4! The exciting part: painting the walls. Finally I can see how the colours will turn out and whether they will match the coastal theme that I’ve in mind. I’ve tried my best to choose fresh colours. 🙂

My contractor also installed the lighting. For lighting, I’ve chosen only 3 that will be the focus points – the 2 pendant lights in the living room and the one that will be above the dining table. All 3 give me a natural feel, so I think they should be able to tie in the fresh coastal theme.

Renovation Process: Week Three

10 Dec

The re-wiring was done during Week 3 and I’ve also arranged for the OpenNet to come down to install the termination point. Remember to always do these concurrently and work closely with your contractor when to get OpenNet people to come down.

This slideshow requires JavaScript.

It was also time to choose the wall paint, window grille design, toilet door design as well as the kitchen cabinet laminate and countertop. So exciting! This is the crucial part whereby my decisions will determine whether the coastal theme is achievable.

Wall Paint

Plan: I wanted light turquoise for the living room. Lime green for the bedrooms.

Actual: There’s no light turquoise in the Dulux Pentalite series that my contractor provided. In the end, I chose Light Topaz which is the closest shade that I can get. But Light Topaz is not available in the Pentalite series, so I have to ask them to mix the paint to get the colour. There’s no extra cost for this service though. My bedroom will be in Cool Lime and my parents chose Cornfield.

Kitchen Cabinet Laminate and Countertop

Plan: I wanted white cabinets with dark brown wooden countertop.

Actual: Wooden countertop is out for my tightly budgeted quotation. So the next best thing is a dark coloured solid surface. I still went with the white cabinet but I decided to put a twist to it. My contractor suggested using a wood grain laminate with a white countertop for my cabinets and showed me what he did for a customer. It looked great, however, as my flooring is dark, I really want the idea of a white cabinet with a dark countertop. So,I decided that the main cabinet with the stove and sink will be white. The side cabinet opposite it will be wood grain. I like the idea as the cabinets will not end up looking too matching. Let’s hope it’ll turn out well! Keeping my fingers crossed! 🙂

*******************************************************************************************************************

Here’s a link to some advice from Rebecca Robeson on how to custom make cabinets for kitchens:

http://www.thedesignnetwork.com/viewVideo.php?video_id=94&video_type=TDN

Renovation Shopping: Week Two

9 Dec

My contractor recommended Chelsea Lighting to buy my lights. After some research on the Internet, I found 2 other lighting shops in the same block as Chelsea. They are Hylite Deco and Pan Tech Lighting. So, I decided to give these 3 shops a visit and compare the prices.

I visited Chelsea Lighting first, they quoted me around $900. I then moved to Hylite Deco which have the same kind of lighting as Chelsea. They quoted me $800. My last stop was Pan Tech. They have very different collections from the other two. The lady there quoted me $600 plus. I was thrilled at the low pricing and decided to buy from Pan Tech. Moreover, the lady said that they used Phillips bulbs. However, as she wrote the invoice, she realised that she miscalculated and said that it should be $700 plus. I thought that was still not so bad and she started calculating again and realised it should be $800 plus. I was very unimpressed by this unprofessional service and decided not to buy from them. In the end, I bought the lights from Hylite Deco who gave the lowest quotation.

Here’s my list of lighting:

  1. Pendant drum light (2)
  2. Pendant light (1)
  3. Round light (1)
  4. Square light (2)
  5. Bulb and holder (3)

2013-12-01 12.33.20

However, I do have a minor complain about Hylite Deco. They told me that they will give me Osram bulbs but in the end, only the pendant drum lights came with Osram bulbs. The rest are fitted with Liyoda bulbs, a brand that I’ve never heard of.

*******************************************************************************************************************

Chelsea Lighting, Hylite Deco and Pan Tech Lighting

353 Jurong East Street 31, Singapore 600353

Renovation Process: Week Two

8 Dec

At the end of the second week, the floor tiles for the kitchen and toilets are laid. The rubbish chute had been fitted in too. The rest of the house has been plastered. The windows have also been installed. The concrete base for the sink has also been built with the sink fitted. A good deal of work done!

This slideshow requires JavaScript.

We also decided on the number and the location of the lighting points and power points. And do take note that lighting points and power points are charged by the numbers. So, if you have more points, the rewiring cost will be higher. Usually, the contractor would have given an estimation in the quotation. And yes, my 3rd shopping task is to shop for lighting. 🙂

Renovation Shopping: Week One

8 Dec

My 2nd shopping task: Buying sanitary ware and kitchen ware. My contractor recommended Chuan Heng Hardware which is located at Jalan Besar. There are quite a few other hardware stores along Jalan Besar and I intended to go there and explore. However, due to my busy schedule at that time, I could only shopped at Chuan Heng Hardware.

The lady who served me was very helpful. My contractor gave me a list of items that I need to buy and I just go according to the list and asked her for recommendations. I also informed her about my budget and asked her questions. It helped that I did a bit of research before I went down.

In the end, here’s my list:

  • 1 set of Hobz hob and hood
  • 1 set of Elleci composite kitchen sink + 2 arm tap
  • 2 sets Munich bathroom accessories
  • 2 sets of basin + pop-up waste + Lubben tap
  • 2 sets of water heater
  • 2 sets of MaClaire WC

I got all these for quite a reasonable price , within my estimated $3K budget.

sink

********************************************************************************************************************

Here are other hardware stores at Jalan Besar that you can go to:

  • GR link Marketing
  • Hoe Kee Hardware

Renovation Process: Week One

7 Dec

Finally! On 31 Oct, the renovation started after we have chosen an auspicious day to start work. According to the Chinese calendar, that is a good day to do construction work. Not that I’m superstitious but my father is very particular about this. Little to his knowledge, that day is actually Halloween Day! For me, I’m glad that he doesn’t know else I may have to push back my renovation!

The first week is pretty much unexciting for me. My contractor, Mr Yeak demolished the existing wall tiles and flooring in the kitchen and the toilets. They then lay the wall tiles of the kitchen and the toilets. I must say their tiling skills are pretty good. I can’t really see the dividing lines between the tiles.

20131109_160708

However, I do have an interesting task for Week One, that is to buy the sanitary ware, sinks, taps, kitchenware and bathroom accessories. Look out for my next post on shopping! 😉